How to Update Task Configuration in DM

Note:
This topic has been translated from a Chinese forum by GPT and might contain errors.

Original topic: dm 如果更新任务配置

| username: Hacker_suny

[TiDB Usage Environment] POC
[TiDB Version] 4.0
[Encountered Problem: Problem Description and Impact]
There is a database with 5 tables. When the task was started, only 3 of the tables were configured for synchronization. Later, a new table was added to MySQL (currently there are 6 tables). Now, we need to synchronize this newly added table to the downstream TiDB. I would like to ask how to update the task in this situation.

| username: Meditator | Original post link

Generally, a new synchronization task is added.